News

Get all your Ghana news, publication and media links here!   Home

 

 

 

Travel & Tourism

 

 

Write to us

 
 

 

 

Read about the free tuition essay competition for university students

 
 
 
 
 
 
 

 

Readings from the budget, affordable housing policy on course - Baah-Wiredu

Accra, Nov. 15, GNA - The Ministry of Water Resource, Works and Housing is committed to the achievement of the Millennium Development Goal (MDG) of 73 per cent of water coverage by 2015, and the Ghana Growth and Poverty-Reduction Strategy objective of 85 per cent coverage by 2015.


Mr Kwadwo Baah-Wiredu, Minister of Finance, Economic Planning, in his budget presentation said the target to deliver 100,000 housing units in all the regional capitals and some district capitals within a period of five years was on course.


He said the final draft of the National Housing Policy was completed and submitted to Cabinet for consideration and approval and the concerns raised by Cabinet sub-committee on infrastructure were being addressed.


The Minister said in line with the policy to provide safe, decent and affordable housing for all people in Ghana, the Ministry continued with the construction of 1,500 flats each at Borteyman and Kpone; 1,192 flats at Asokore-Mampong; 200 flats at Tamale and 400 flats at Koforidua.


"The Ministry has also commenced the construction of 150 flats each at Wa and Bolgatanga. The housing units are at various stages of completion.
Mr Baah-Wiredu announced that the construction of the Affordable Housing Units would commence in Sekondi-Takoradi, Sunyani, Cape Coast and Ho early next year.


He said the Ministry continued the sale of Government Low Cost Houses throughout the country with the view to using the revenue accrued to increase the stock of decent, safe and affordable houses for workers.


He said so far about 5,000 units had been offered for sale.


The Minister said the Ministry was working on the restoration of the
Peduase Lodge and the main structural, civil, electrical, mechanical, air-condition works were completed.


"Work on special furnishings, fixtures, fittings and draperies as well as painting are ongoing. External civil works, telephone system, horticultural, lighting and security as well as auxiliary works are also ongoing," he said.


On the Keta Sea Defence Resettlement Programme, he said the 84.0 million dollars project comprising six groynes; a 783-metre revetment; 8.5 kilometre main link and cross roads between Havedzi and Keta; 272 hectares of land reclaimed and a 20 bay flood control structure had been completed and were functional.


He said the construction of 836 resettlement houses for displaced inhabitants was ongoing. Since its implementation, 254 houses out of the contracted 444 had been completed and occupied with the remaining 190 houses at various stages of completion.


He said water supply had been extended to the resettlement sites at Kedzi, Vodza and Adzido and work on the sewerage system was also progressing steadily with about 50 houses, which had been connected at Adzido.
The Minister said transmission of electricity to the site was also completed.

 

On rural water, Mr Baah-Wiredu said the Community Water and Sanitation Agency (CWSA) had dug 283 new boreholes; 63 hand-dug wells; 111 boreholes and rehabilitated nine hand-dug wells; executed 30 small towns piped schemes and 24 others at various stages of completion.


The CWSA also constructed 1,904 household and 127 institutional latrines during the year under review.


Mr Baah-Wiredu said water supply improvement to some educational institutions in the Central Region namely, St.


Augustine College; Mfantsipim; Adisadel; Aggrey Memorial; Wesley Girls; Ghana National; Edinaman; the University of Cape-Coast and the Ankaful Psychiatric Hospital had been completed.


He said work on the Kwanyaku Water Supply System had also been completed and inaugurated. This has increased the output of water from the present three million gallons a day to six million gallons.


"Over 700,000 people at Kwanyaku and its environs are benefiting from the facility," he said.


He announced that work on the East-West Water Transfer Interconnection, which started in March 2007 was about 35 per cent completed, and work was progressing steadily.


"Site preparation for the treatment plant; excavation work for the construction of filters and clarifiers; pipe-laying from the Okponglo Booster Station and pipe-laying to Atomic Junction have all been completed.


"Pipe-laying through the Achimota Forest en-route to the Okponglo Booster Station is ongoing. The project when completed will provide water to the Eastern parts of Accra - Achimota, Taifa, Dome, Tantra Hill, Ofankor, Amasaman," he said.


Mr Baah-Wiredu said the Cape Coast Water Supply Expansion Project would draw water from Sekyere Hemang and supply potable water to all towns en-route to Cape Coast.


He said work on the Tamale Water Supply Expansion was in progress with the laying of pipelines to the new water treatment plant as well as undertaking water assets management.


The Minister said work started on the Koforidua Water Supply Project in May after receipt of advance payment and the final design of the works was completed and actual construction has started.


The project is expected to be completed in November 2009.


On Urban Water Project (UWP), he said, Mr Baah-Wiredu said the GWCL management contract operator was in its second year of operation. The procurement of works, pipe-laying and associated works, vehicles for operations and office equipment have all been completed.

 

 Mr Baah-Wiredu announced that the Ministry was in consultation with Messrs Coman Engineering and Contracting of the Netherlands for the Wa Water Supply Project at a total cost of 39 million euros.


He said to further improve upon water supply to Adenta and its environs, GWCL was to carry out a second phase of the Adenta Water Supply Improvement Works.


Newly developing communities that lie between Dodowa and Adenta were also to benefit from the project.


On the Kumasi Water Supply Project, he said, Messrs Taylor Woodrow had completed all processes in the financing and was undertaking further expansion works to Barekese on a turnkey basis.


The design and construction works had commenced and the contractor was mobilizing to site, he said, adding that the consultant for the supervision of the project had also been selected.


Mr Baah-Wiredu said the African Development Fund had provided funds through the Swedish Government (Swedish Trust Fund) to undertake studies on Water and Sanitation in Wa, Yendi and Damongo.


The objective of the study was to assess water and sanitation requirements of the towns up to the year 2020 in line with the national target in the National Water Sector Policy and the Millennium Development Goals (MDGs) by providing a feasibility study, designing a project and preparing tender documents for immediate implementation, he said.


Touching on the Integrated Odaw Basin Development Project he said, stage III works estimated at about 18 Million euros and involved the removal of the estimated 180,000 m3 accumulated silt and other materials in the approximately 10 kilometre long feeding canals of Kaneshie, Odaw and Agbogbloshie was nearing completion.


"The waste water treatment plant, a 75-metre long interceptor weir and the 2.3-kilometre long new sea outfall pipe have been completed and functional. A pre-feasibility study for a sewerage treatment plant to an expanded scope of KLERP has been completed.


Preparation of feasibility studies, detailed designs and contract document for physical implementation is progressing steadily.”


Mr Baah-Wiredu said 10.4 million euros for the relocation of Sodom and Gomorrah and the bulk market from old Fadama to Adjen Kotoku had been secured and preparatory works

including land acquisition had been completed.


He said work had started on the 12.1 million Euro Elmina Benya Lagoon Restoration Project and so far about 43 per cent of the works on dredging of the 1,200 metre long lagoon and breakwater works have been completed.


He said an assessment on the Ada Coastal Protection Works had been completed since February 2007 on approximately 14 kilometres shoreline stretching from Azizanya to Otrokpe.


About 10 kilometres of the shoreline would be protected by a system of groynes/sand nourishment and four kilometres with a revetment structure including a groyne at the estuary of the Volta river to ensure a permanent opening to allow continuous inflow of sea water.

 

Mr Baah-Wiredu said the channel improvement works as a flood control measure estimated at about 1.25 million euros on the 1,000-metre stretch of the Densu River at Nsawam was nearing completion.


"Flood Control and Coastal Protection Works 590 and the reduction in the incidence of flooding in some parts of the city of Accra have been achieved as a result of channel improvement works undertaken by the Ministry on some primary drains in Accra.


"The Ministry's interventions at some critical areas undergoing sea erosion along the shoreline at Dixcove, Shama and Axim in the Western Region, are ongoing.”


On transportation, The Minister said the Transport Ministry was mandated to ensure the provision of affordable, integrated, safe, responsive, and sustainable road transport system comprising road infrastructure and transport services that will meet the economic, social and environmental needs as well as national and international standards.


Mr Baah-Wiredu said in support of Growth and Poverty-Reduction Strategy (GPRS) II, the 2007 Budget took into consideration the derived objectives of integrating rural and urban economies as well as ensuring lower transport costs through the provision of safe and reliable road infrastructure and services.


He said the Ministry in collaboration with the Ministry of Local Government, Rural Development and Environment (MLGRDE), in September, 2007 launched the Urban Transport Project (UTP) to reduce congestion by modernizing the operation of public transport and traffic managements in some selected major cities.


The project, he said, would be implemented in: Accra Metropolitan Assembly (AMA); Kumasi Metropolitan Assembly (KMA); Tema Municipal Assembly (TMA); Ga East District Assembly (GEDA); Ga West District Assembly (GWDA) and Ejisu Juaben District Assembly (EJDA).


Mr Baah-Wiredu said a Project Advisory Office (PAO) had been set up to coordinate the implementation of this 5-year project.


The office would evolve into a Centre for Urban Transportation by 2010. Project designs have begun for the construction of a pilot Bus Rapid Transit (BRT) route from the Central Business District (CBD) to Mallam in Accra.


He said the Ministry, in collaboration with Ghana Statistical Service (GSS) has completed the development of poverty monitoring indicators for establishing the linkages between poverty reduction and road transport development.


He announced that the Ministry had revised the Road Traffic Regulations this year to operationalise the Road Traffic Act 683 of 2004.


He said the Ghana Highway Authority undertook routine maintenance works of a total of 6,486.08 km and periodic maintenance works of 151.34 km involving re-gravelling/spot improvement and resealing during the year under review.


GNA



 

Rate this article:

The president’s accident and some security implications


Washington, Nov 15, Ghanadot - The accident occurred in the morning while the president was on his way to work on a route he travels daily. If it is an assassination attempt who will it benefit? .....
.....More 

 

Court begins trial on 31st DWM /DAKMAK case

Accra, Nov. 13, Ghanadot/GNA - An Accra Fast Track High Court (FSHC) on Tuesday set out for trial the case in which the 31st December Women's Movement (DWM) is alleged to be illegally occupying a confiscated property belonging to the Dakmak Enterprise..
 .More   

   

Two Venezuelans in 588-kilogramme East Legon cocaine case jailed

Accra, Nov. 13, Ghanadot/GNA - An Accra Fast Track High Court on Tuesday handed jail terms on two Venezuelans connected to the 588 kilogrammes of cocaine seized from a house at Mepeasem, East Legon, Accra   .
...More

 

I thank God I am in one piece” - President Kufuor

Accra, Nov. 14, Ghanadot/GNA - "I thank God, I am in one piece", President John Agyekum Kufuor told newsmen after escaping unhurt in a motor accident involving his convoy at a crossroads on the Airport – 37th Military Hospital Road in Accra, on Wednesday  .......More  

   
 

ABC, Australia
FOXNews.com
The EastAfrican, Kenya
African News Dimensions
Chicago Sun Times
The Economist
Reuters World
CNN.com - World News

All Africa Newswire
Google News
The Guardian, UK
Africa Daily
IRIN Africa
The UN News
Daily Telegraph, UK
Daily Nation, East Africa

BBC Africa News, UK
Legal Brief Africa
The Washington Post
BusinessInAfrica
Mail & Guardian, S. Africa
The Washington Times
ProfileAfrica.com
Voice of America

CBSnews.com
New York Times
Vanguard, Nigeria
Christian Science Monitor
News24.com
Yahoo/Agence France Presse

 
  SPONSORSHIP AD HERE  
 
    Announcements
Debate
Commentary
Ghanaian Paper
Health
Market Place
News
Official Sites
Pan-African Page
Personalities
Reviews
Social Scene
Sports
Travel
 
    Currency Converter
Educational Opportunities
Job Opening
FYI
 
 

 

www.ghanavidia.com

Video expressions from Ghana and the Diaspora

 

 
Send This Page To A Friend:

The Profile Africa Media Group